超深井径向钻孔钛合金管转向阻力计算及安全评估
引用本文:吴春洪,翟科军,万小勇,刘少胡,刘元亮,杨哲.超深井径向钻孔钛合金管转向阻力计算及安全评估[J].中国安全生产科学技术,2022,18(1):63-67.
作者姓名:吴春洪  翟科军  万小勇  刘少胡  刘元亮  杨哲
作者单位:(1.中国石油化工集团公司 碳酸盐岩缝洞型油藏提高采收率重点实验室,新疆 乌鲁木齐 830011;2.中国石油化工股份有限公司 西北油田分公司,新疆 乌鲁木齐 830011;3.长江大学 机械工程学院,湖北 荆州 434023;4.中石化江汉石油工程有限公司 钻井一公司,湖北 潜江 433100)
基金项目:国家自然科学基金项目(51974036);中石化科研项目(P20002)。
摘    要:为了解决塔河油田6000 m及以上深井径向钻孔作业时管柱强度低、无法很好地传递钻压等问题,提出利用修井机和油管、钛合金管进行径向钻孔工艺,并通过数值模拟的方法优选有矫直段的单向弯曲转向轨道,研究轨道转向半径、钛合金管外径及壁厚、轨道与管柱间隙对钻进能力的影响,其次,通过正交试验方法,对上述参数进行敏感度分析并进行参数优...

关 键 词:径向钻孔  钛合金管  超深井  轨道

Steering resistance calculation and safety evaluation of titanium alloy pipe in radial drilling of ultra-deep well
WU Chunhong,ZHAI Kejun,WAN Xiaoyong,LIU Shaohu,LIU Yuanliang,YANG Zhe.Steering resistance calculation and safety evaluation of titanium alloy pipe in radial drilling of ultra-deep well[J].Journal of Safety Science and Technology,2022,18(1):63-67.
Authors:WU Chunhong  ZHAI Kejun  WAN Xiaoyong  LIU Shaohu  LIU Yuanliang  YANG Zhe
Institution:(1.Key Laboratory of Enhanced Oil Recovery in Carbonate Fractured-vuggy Reservoirs,CNPC,Urumqi Xinjiang 830011,China;2.SINOPEC Northwest Oil Field Company,Urumqi Xinjiang 830011,China;3.School of Mechanical Engineering,Yangtze University,Jingzhou Hubei 434023,China;4.No.1 Drilling Company,Sinopec Jianghan Petroleum Engineering Co.,Ltd.,Qianjiang Hubei 433100,China)
Abstract:In order to solve the problems of low strength of the pipe string and inability to transmit the weight on bit during the radial drilling operation in deep wells of 6000 m and above in Tahe Oilfield,a radial drilling technology using workover rigs,oil pipes and titanium alloy pipes was proposed.The unidirectional curved steering track with straightening section was optimized through numerical simulation,and the influence of track steering radius,outer diameter and wall thickness of titanium alloy pipe,clearance between track and pipe string on the drilling capacity was studied.Through the orthogonal experiment method,the sensitivity analysis on the above parameters and the parameter optimization were conducted.The results showed that the track steering radius and the clearance were inversely proportional to the steering resistance,while the outer diameter and wall thickness of the titanium alloy pipe were positively proportional to the steering resistance.The combined parameters of the titanium alloy pipe and steering gear track were recommended as follows:the track steering radius was 600 mm,the steering angle was 30°,the outer diameter of the titanium alloy pipe was 25 mm,the wall thickness was 2 mm,and the clearance between the titanium alloy pipe and steering gear track was 4 mm.
Keywords:radial drilling  titanium alloy pipe  ultra-deep well  track
本文献已被 维普 等数据库收录!
点击此处可从《中国安全生产科学技术》浏览原始摘要信息
点击此处可从《中国安全生产科学技术》下载免费的PDF全文