火电厂石灰石-石膏脱硫设施环保验收监测若干问题的探讨
引用本文:伍震威,单平,黄界颍,刘静思.火电厂石灰石-石膏脱硫设施环保验收监测若干问题的探讨[J].中国环境监测,2013,29(5):146-149.
作者姓名:伍震威  单平  黄界颍  刘静思
作者单位:安徽省环境监测中心站, 安徽 合肥 230071;安徽省环境监测中心站, 安徽 合肥 230071;安徽农业大学资源与环境学院, 安徽 合肥 230036;安徽省环境监测中心站, 安徽 合肥 230071
摘    要:以"十一五"期间较为常见的火电厂石灰石-石膏脱硫设施竣工环保验收监测为例,着重就验收过程监测布点、设施处理效率计算、污染物总量核算、减排项目标准执行以及环境管理检查中存在的问题进行探讨,提出解决问题的方法与思路,为今后火电厂竣工环保验收监测工作提供借鉴。

关 键 词:火电厂  石灰石-石膏脱硫  环保验收监测
收稿时间:2012/2/22 0:00:00
修稿时间:2012/6/26 0:00:00

Problems on Environmental Protection Acceptance Monitoring of Limestone-Plaster Desulphurization Facility of Thermal Power Plant
WU Zhen-wei,SHAN Ping,HUANG Jie-ying and LIU Jing-si.Problems on Environmental Protection Acceptance Monitoring of Limestone-Plaster Desulphurization Facility of Thermal Power Plant[J].Environmental Monitoring in China,2013,29(5):146-149.
Authors:WU Zhen-wei  SHAN Ping  HUANG Jie-ying and LIU Jing-si
Institution:Anhui Environmental Monitoring Centre, Hefei 230071, China;Anhui Environmental Monitoring Centre, Hefei 230071, China;College of Resources and Environment, Anhui Agricultural University, Hefei 230036, China;Anhui Environmental Monitoring Centre, Hefei 230071, China
Abstract:Taking the common environmental protection acceptance monitoring of limestone-plaster desulphurization facility in the thermal power plant during the period of the "eleventh five-year plan" as an example, discussed on the problems of acceptance process, such as monitoring sites, calculation of facility treatment efficiency, total accounting of pollutants, execution of emission reduction standard and environmental management examination, and proposed solutions and solving thoughts, it is worth to use for reference in environmental protection acceptance monitoring of thermal power plant in the future.
Keywords:thermal power plant  limestone-plaster desulphurization  environmental protection acceptance monitoring