R/S法的土石坝施工期沉降规律及预警标准研究
引用本文:张社荣,韩启超,谭尧升,撒文奇.R/S法的土石坝施工期沉降规律及预警标准研究[J].中国安全科学学报,2012(8):164-170.
作者姓名:张社荣  韩启超  谭尧升  撒文奇
作者单位:天津大学水利工程仿真与安全国家重点实验室
基金项目:国家创新研究群体科学基金资助(51021004)
摘    要:为提高施工期土石坝沉降安全性,研究其具有复杂非线性特征的施工期沉降规律和相应的预警标准。基于国内某在建高土石坝的沉降数据,采用R/S法分析坝体不同高程测点、同高程测点和同测点不同时期沉降数据的Hurst指数及分形维数,提出评价坝体施工期沉降安全性的预警标准。结果表明:各测点的Hurst指数最小值为0.763,坝内各处沉降仍处于快速增长阶段;坝体下部比上部、中部比下游堆石区沉降能更快趋于稳定,且坝体下部的沉降速率已经渐趋平缓。

关 键 词:土石坝  沉降  重标度极差分析(R/S)法  Hurst指数  分形维数  预警标准

An R/S Method-based Study on Settlement Regularity and Warning Standard of Earth-rock Dam during Construction
ZHANG She-rong,HAN Qi-chao,TAN Yao-sheng,SA Wen-qi.An R/S Method-based Study on Settlement Regularity and Warning Standard of Earth-rock Dam during Construction[J].China Safety Science Journal,2012(8):164-170.
Authors:ZHANG She-rong  HAN Qi-chao  TAN Yao-sheng  SA Wen-qi
Institution:(State Key Laboratory of Hydraulic Engineering Simulation and Safety,Tianjin University, Tianjin 300072,China)
Abstract:In order to improve the settlement safety of earth-rock dam during construction,the complex non-linear settlement regularity and the corresponding warning standard were studied.Based on settlement data of a certain domestic high earth-rock dam in construction,applying R/S method,Hurst index and fractal dimension of the settlement data from different elevation points,the same elevation points and the same point in different periods were analyzed,warning standard to evaluate settlement safety during construction was proposed.The results show that the minimum Hurst index is 0.763,and dam settlement is still in the fast growth stage;the settlement in dam bottom can tend to be stable faster than the upper,also the middle than the downstream rock-fill area,and dam settlement rate in bottom has been gradually gentle.
Keywords:earth-rock dam  settlement  rescaled range analysis(R/S) method  Hurst index  fractal dimension  warning standard