Analysis of underlying causes of investigated loss of containment incidents in Dutch Seveso plants using the Storybuilder method
Authors:Linda J Bellamy  Martijn Mud  Henk Jan Manuel  Joy IH Oh
Institution:1. White Queen Safety Strategies, PO Box 712, 2130 AS Hoofddorp, The Netherlands;2. RPS, PO Box 5094, 2600 GB Delft, The Netherlands;3. Dutch National Institute for Public Health and the Environment (RIVM), PO Box 1, 3720 BA Bilthoven, The Netherlands;4. Ministry of Social Affairs and Employment (SZW), PO Box 90801, 2509 LV Den Haag, The Netherlands
Abstract:In the Netherlands there are around 400 “Seveso” sites that fall under the Dutch Major Hazards Decree (BRZO) 1999. Between 2006 and 2010 the Dutch Labour Inspectorate's Directorate for Major Hazard Control completed investigations of 118 loss of containment incidents involving hazardous substances from this group. On the basis of investigation reports the incidents were entered in a tailor-made tool called Storybuilder developed for the Dutch Ministry of Social Affairs and Employment for identifying the dominant patterns of technical safety barrier failures, barrier task failures and underlying management causes associated with the resulting loss of control events. The model is a bow-tie structure with six lines of defence, three on either side of the central loss of containment event. In the first line of defence, failures in the safety barriers leading to loss of control events were primarily equipment condition failures, pre start-up and safeguarding failures and process deviations such as pressure and flow failures. These deviations, which should have been recovered while still within the safe envelope of operation, were missed primarily because of inadequate indication signals that the deviations have occurred. Through failures of subsequent lines of defence they are developing into serious incidents. Overall, task failures are principally failures to provide adequate technical safety barriers and failures to operate provided barriers appropriately. Underlying management delivery failures were mainly found in equipment specifications and provisions, procedures and competence. The competence delivery system is especially important for identifying equipment condition, equipment isolation for maintenance, pre-start-up status and process deviations. Human errors associated with operating barriers were identified in fifty per cent of cases, were mostly mistakes and feature primarily in failure to prevent deviations and subsequently recover them. Loss of control associated with loss of containment was primarily due to the containment being bypassed (72% of incidents) and less to material strength failures (28%). Transfer pipework, connections in process plant and relief valves are the most frequent release points and the dominant release material is extremely flammable. It is concluded that the analysis of a large number of incidents in Storybuilder can support the quantification of underlying causes and provide evidence of where the weak points exist in major hazard control in the prevention of major accidents.
Keywords:Accidents  Bow-tie  Human error  Incidents  Loss of containment  Major hazards  Safety barriers  Safety management  DLI"}  {"#name":"keyword"  "$":{"id":"kwrd0055"}  "$$":[{"#name":"text"  "_":"Dutch Labour Inspectorate  ESAW"}  {"#name":"keyword"  "$":{"id":"kwrd0065"}  "$$":[{"#name":"text"  "_":"European Statistics on Accidents at Work Methodology  IDDR"}  {"#name":"keyword"  "$":{"id":"kwrd0075"}  "$$":[{"#name":"text"  "_":"Indication Detection Diagnosis Response  LCE"}  {"#name":"keyword"  "$":{"id":"kwrd0085"}  "$$":[{"#name":"text"  "_":"Loss of control event  LOC"}  {"#name":"keyword"  "$":{"id":"kwrd0095"}  "$$":[{"#name":"text"  "_":"Loss of containment  SZW"}  {"#name":"keyword"  "$":{"id":"kwrd0105"}  "$$":[{"#name":"text"  "_":"Dutch Ministry of Social Affairs & Employment
本文献已被 ScienceDirect 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号