阿海水电站新源沟砂石加工废水处理工艺浅谈
引用本文:陈庆中,欧阳湘龙,石磊.阿海水电站新源沟砂石加工废水处理工艺浅谈[J].四川环境,2012(1):55-58.
作者姓名:陈庆中  欧阳湘龙  石磊
作者单位:[1]金沙江中游水电开发有限公司,昆明650228 [2]中国水利水电建设工程咨询西北公司,西安710075
摘    要:新源沟砂石加工系统生产废水SS浓度高,采用水力旋流/加药絮凝/多级沉淀工艺处理,运行结果表明,处理出水水质满足《污水综合排放标准》(GB8978-1996)一级标准中的给定限值70mg/L,达标出水全部回用。

关 键 词:砂石加工废水  悬浮物  絮凝多级沉淀工艺  回用

Treatment of Wastewater from Artificial Aggregate Processing System in Xinyuangou of Ahal Hydropower Station
CHEN Qing-zhong,OUYANG Xiang-long,SHI Lei.Treatment of Wastewater from Artificial Aggregate Processing System in Xinyuangou of Ahal Hydropower Station[J].Sichuan Environment,2012(1):55-58.
Authors:CHEN Qing-zhong  OUYANG Xiang-long  SHI Lei
Institution:1. Jinsha River Middle Reaches Hydropower Corporation, Kunming 650228, China; 2. China Northwest Water Conservancy & Hydropower Engineering Consulting Company, Xi'an 710075, China)
Abstract:The wastewater from the Artificial Aggregate Processing System in Xinyuangou contains high concentration SS, which is treated adopting processes including hydrocyclone, flocculation and multi-level sedimentation. The operation result shows that the effluent quality reaches the first level criteria 70mg/L that is specified in Integrated Wastewater Discharge Standard (GB 8978-1996), so all of the effluent is recycled for reuse.
Keywords:Wastewater from artificial aggregate processing system  suspended solids (SS)  flocculation and multi-level sedimentation  reuse