基于RBI技术的海上平台延期服役静设备定量化安全评估技术
引用本文:李毅,詹燕民,轩军厂,吴奇兵. 基于RBI技术的海上平台延期服役静设备定量化安全评估技术[J]. 中国安全生产科学技术, 2013, 0(10): 121-126
作者姓名:李毅  詹燕民  轩军厂  吴奇兵
作者单位:[1]中海石油(中国)有限公司天津分公司,天津300452 [2]中海油安全技术服务有限公司,天津300456
基金项目:中海石油(中国)有限公司科研项目
摘    要:针对海上延期服役平台静设备的安全风险评估与控制问题,应用RBI风险评估技术的评估理论和方法对海上延期服役平台静设备的定量化安全管理方法进行了实践和探索,并选择某延期服役平台进行风险分析相关结论的工程验证。其具体过程是运用定量RBI技术,首先根据工艺流程和介质特点对海上平台静设备分别进行了物流回路和损伤回路的划分,并以此为基础对延期服役平台静设备的安全风险进行定量评估,进而得出各静设备单元的失效可能性、失效后果及风险等级,最后通过得出的损伤模式、损伤机理及对应的腐蚀速率,从而制定针对性的检测策略。将利用这些检验策略所检测出的真实情况与分析结论进行对比,最终验证了RBI技术在延期服役平台静设备风险评估方面具有很强的适用性。

关 键 词:延期服役  RBI检测  风险评估  静设备  检测策略

Exploration and application of RBl-based quantitative safety assessment technology for static equipment in extended service on offshore platform
LI Yii,ZHAN Yan-minI,XUAN Jun-chang,WU Qi-bing. Exploration and application of RBl-based quantitative safety assessment technology for static equipment in extended service on offshore platform[J]. Journal of Safety Science and Technology, 2013, 0(10): 121-126
Authors:LI Yii  ZHAN Yan-minI  XUAN Jun-chang  WU Qi-bing
Affiliation:2 Tianjin Branch of China National Offshore Oil Corporation Limited, Tianjin 300452, China; 2. CNOOC Safety and Technology Services Co. , LTD, Tianjin 300456, China)
Abstract:Aiming at the safety risk assessment and control of static equipment on offshore platform in extended service, the assessment theories and methods of RBI risk assessment technology was applied to implement and ex- plore the quantitative safety management methods of static equipment on offshore platform in extended service. A platform in extended service was selected for the verification of conclusions associated with risk analysis. The spe- cific process was to apply quantitative RBI technology. Firstly, the static equipments on offshore platform were clas- sified into two categories-logistic loop and damage loop-according to the characteristics of processes and media, which was then used as basis for the quantitative safety risk assessment of static equipment on offshore platform. Then the probability of failure, consequence of failure and risk level were estimated. In the end, the damage mode, damage mechanism, and corresponding corrosion speed were calculated to develop targeted testing strategy. The practical conditions obtained through such testing strategy were then compared with the conclusion of the analysis. The comparison results showed that RBI technology has a good applicability in risk assessment of static equipment on extended service offshore platform.
Keywords:extended service  RBI testing  risk assessment  static equipment  testing strategy