首页 | 本学科首页   官方微博 | 高级检索  
     

既有大型公共设施改造下紧邻深基坑开挖变形分析*
引用本文:孙廉威,颜超,程子聪. 既有大型公共设施改造下紧邻深基坑开挖变形分析*[J]. 中国安全生产科学技术, 2020, 16(11): 96-102. DOI: 10.11731/j.issn.1673-193x.2020.11.015
作者姓名:孙廉威  颜超  程子聪
作者单位:(上海建工集团股份有限公司,上海 201114)
基金项目:* 基金项目: 国家重点研发计划项目(2017YFC0805500);上海建工集团股份有限公司重点科研项目(18JCSF-28)
摘    要:为探索深基坑开挖与紧邻大型公共设施改造的相互影响,确保施工安全,基于上海体育馆改造及新建地下体育综合体工程,采用有限元软件Plaxis对紧邻深基坑工程大型公共设施“卸载-加载”改造过程进行模拟,详细分析上海体育馆“卸载-加载”改造与紧邻综合体深基坑开挖同时进行对基坑本体及上海体育馆的安全影响,并在此基础上探讨紧邻深基坑工程大型公共设施改造最优工序。结果表明:在基坑开挖至第2道支撑时进行加载改造为最不利工况,且围护结构侧向位移将超过规范允许值,在施工中应严格避免;最优工序为完成第1道支撑后进行卸载改造,完成第2道支撑后进行加载改造。

关 键 词:深基坑开挖  大型公共设施改造  数值模拟  安全影响  最优工序

Deformation analysis of deep foundation pit excavation adjacent to reconstruction of existing large public facility
SUN Lianwei,YAN Chao,CHENG Zicong. Deformation analysis of deep foundation pit excavation adjacent to reconstruction of existing large public facility[J]. Journal of Safety Science and Technology, 2020, 16(11): 96-102. DOI: 10.11731/j.issn.1673-193x.2020.11.015
Authors:SUN Lianwei  YAN Chao  CHENG Zicong
Affiliation:(Engineering General Institute,Shanghai Construction Group Co.,Ltd.,Shanghai 201114,China)
Abstract:In order to explore the interaction effect between the deep foundation pit excavation and the reconstruction of adjacent large public facility,thus ensure the construction safety,the finite element software Plaxis was used to simulate the “unloading loading” reconstruction process of a large public facility adjacent to deep foundation pit engineering based on the project of Shanghai gymnasium reconstruction and new underground sports complex construction.The safety influence of the simultaneous Shanghai gymnasium “unloading loading” reconstruction and the deep foundation pit excavation of adjacent complex on the foundation pit itself and Shanghai gymnasium was analyzed in detail,and on this basis,the optimal process of large public facility reconstruction adjacent to deep foundation pit engineering was discussed.The results showed that the most unfavorable condition was to carry out the loading reconstruction when the foundation pit was excavating to the second support,and the lateral displacement of retaining structure would exceed the allowable value of the code,which should be strictly avoided during the construction.The optimal construction process was to carry out the unloading reconstruction when finishing the first support,and carry out the loading reconstruction when finishing the second support.
Keywords:deep foundation pit excavation   reconstruction of public facility   numerical simulation   safety impact   optimal construction process